Showing posts with label building codes. Show all posts
Showing posts with label building codes. Show all posts

Friday, August 31, 2018

Top 10 Significant Modifications to the 2018 IRC

Last week the S.C. Building Codes Council met to review dozens of proposed changes to the International Series of building codes, including the International Residential Code, the building code that applies to one- and two-family dwellings in South Carolina.

Your Home Builders Association, working with your Home Builders Association of South Carolina, proposed several modifications, including one that would have removed Arc-Fault Circuit Interrupters from the building code.

Below is a list of the top 10 significant changes and modifications to the 2018 IRC.  These changes, as well as dozens of others, will be presented to the General Assembly in January.  The effective date of the new building code is expected to be January 1, 2020.
  1. Sections 301.2 and 301.2.2.1-Wind & Seismic Maps. The HBA of SC supported a study to be funded by the S. C. General Assembly and produced by The Citadel to review and address the probabilistic hazard maps. This will ensure that houses in S. C. are built on the needs and hazards of our state. 
  2. Section 301.2.1.2 Protection of openings. This change replaces 2-story limit on use of wood structural panels for wind-borne debris protection with limit based on 45-foot mean roof height. 
  3. Section 302.1 Exterior Walls. This modification maintained the minimum fire separation distance for improvements constructed on a lot where the local governing authority has prior to the implementation of IRC 2012. 
  4. Section 302.5.1 Opening Protection. The existing modification was maintained to remove the use of a selfclosing device. 
  5. Section 313 One-and -Two Family Dwellings Automatic Fire Systems. This modification maintains that residential fire sprinklers continue to be an option, but are not mandated. 
  6. Section R318.1 Protection Against Subterranean Termites. This modification adds an additional method to allow treatments to be conducted under the S.C. Pesticide Control Act and enforced by the Clemson University Department of Pesticide Regulation. 
  7. Section R318.4 Foam Plastic Protection. This modification adds language to allow foam plastics to provide an inspection gap for crawlspace applications. 
  8. Section M1502.4.2 Duct Installation. Language would allow exhaust ducts to be supported at intervals not to exceed 8 feet and ducts will no longer be required to be joined with screws. 
  9. Appendix Q Tiny Houses. By adding Appendix Q builders will have more options and flexibility for small home construction. 
  10. Section E3902.16 Arc-Fault Circuit Interrupter Protection. Language rolls back code to earlier version that would remove the use of AFCIs in kitchens and laundry rooms.
Be sure to thank these members, who have served on your HBA's Building Codes Committee and have actively support the work of reviewing and modifying the new building code:
  • Matt Shouse, APB, Chairman
  • Mike Freeman, APB, member of the NAHB Building Codes and Standards Committee
  • Joe Hoover, APB
  • Matt Ruth, APB
  • Rick Quinn, APB
  • Steve Carson, APB
  • James Speer, APB
  • Lee Hornbeck, APB

Thursday, June 23, 2016

Building Codes Class for the New Code, Effective July 1

The S.C. General Assembly has signed off on a new Residential Building Code for South Carolina, the 2015 IRC. It takes effect on July 1, 2016!

Your HBA held a Building Codes Class on this new building code in February, so many of you are already prepared. For those of you who are not, below are opportunities we are developing in the next couple of months to get you ready:
  • John McLeod, Chief Building Official for Greenville County, will host a workshop on the new codes on Tuesday, June 28, 9 a.m. until 11 a.m., in Conference Room D, Greenville County Square. He will review and highlight the important code changes and of course offer his enforcement interpretations.
  • Your HBA is working with John and Buddy Skinner, Chief Building Official for the City of Greenville, on a second opportunity in early July. 
  •  And your HBA will also have Andy Barber, HBA of South Carolina Building Codes Chairman, back in Greenville in early August for a repeat of the four-hour code training class he offered in February.

Note that the new building code is effective for permits issued on or after July 1. Houses already permitted or for which a permit was applied for on or before June 30 will still be subject to the 2012 IRC.

Note, however, that you may find that several of the statewide code amendments that were secured by your Home Builders Association make the new code an improvement in many respects. You can review the statewide amendments by clicking here.


Code Books Available Through Your HBA

Your HBA can help you receive the ICC member discount on code books, thanks to Buddy Skinner who has offered to place the order for us. If you would like to order your code book in this manner, please review the code book options at iccsafe.org and email your code book requests to mdey@hbaofgreenville.com. Your order is due by June 28 at 5 p.m. Plan on a week for the code books to be delivered.


Monday, June 13, 2016

2015 Building Codes Adoption

The list of modifications to the 2015 editions of the International Code series has completed the legislative process as required by law. The projected date for implementation is July 1, 2016. Any projects that have permit approval prior to July 1, 2016 may be completed using the 2012 series. I want to thank the members of the HBA Building Codes Committee for their hard work to modify the code. Their work has allowed a much more manageable code to be implemented in S.C.

List of the modifications to the 2015 Building Codes

Friday, May 29, 2015

New Requirements Announced for Federally Insured Construction

New energy-efficiency requirements as part of the Energy Independence and Security Act of 2007 go into effect this summer for new single- and multifamily homes insured through or with financing provided by some federal housing programs.

All homes using the programs must meet the requirements of either the 2009 International Energy Conservation Code or ASHRAE 90.1 Standard for energy efficiency.

Because the requirements are keyed to updates in the model building codes, the departments of Housing and Urban Development and Agriculture – the two agencies that administer the affected programs – estimate that the new standards will affect about 3,200 multifamily and 15,000 single-family units per year.

That is because the new rules only affect homes built in jurisdictions that have not yet adopted the 2009 International Energy Conservation Code for single-family or low-rise multifamily (three stories or less) or the 2007 ASHRAE 90.1 standard for mid- and high-rise multifamily construction.

South Carolina has adopted the 2009 IECC.

The Department of Energy says that only 12 states have building codes not meeting the requirements, although some jurisdictions within those states may already exceed them.

Excluded are homes built under HUD’s Housing Choice Voucher Program, Indian Housing Programs, Community Development Block Grant Funds, or USDA multifamily housing programs.

HUD and USDA also will accept certain programs and properties as being in compliance if they meet equivalent or higher energy-efficiency standards. This includes homes built under the Public Housing Capital Fund, Section 811 Supportive Housing, Choice Neighborhoods and any unit built to Energy Star, Enterprise Green Communities, LEED or the performance path of the ICC-700 National Green Building Standard.

The agencies issued a Notice of Final Determination earlier this month establishing the standards as well as a timeline for when they are effective.

The notice included a nod to the National Association of Home Builders’s comments written last year when the preliminary determination was unveiled: NAHB asked for more time to allow builders and developers to make changes to their plans, and the final notice allows four months after the May 6 effective date for developers to file for FHA insurance under the existing program and grandfathers in seven months for single-family builders that already have obtained building permits.

It also acknowledges NAHB’s request to ensure cost effectiveness in any new requirements, estimating that the changes result in a payback of 5.2 years for low-rise residential, well within NAHB policy of 10 years.

Thursday, January 8, 2015

‘Clean Power’ Regs Delayed

Proposed – and very controversial – plans to tighten regulations governing emissions from America’s power plants will not become final until sometime mid-summer, the Environmental Protection Agency announced yesterday.

Your Home Builders Association submitted more than a hundred pages of comments on the proposal in December, and the agency had planned to finalize its regulations by June 15, 2015.

While the sweeping regulations target power plants, they would have repercussions for home builders, who could be targeted with much tighter building code requirements if the draft rule becomes final.

However, as the National Association of Home Builders said in its comments, stricter energy codes would affect only new construction, not the millions of older homes not built to today’s higher standards, and EPA has no authority over building codes in the first place.

In addition, no agency or regulatory body can control how much electrical power a home owner decides to use once the building is occupied.

Monday, December 29, 2014

Changes Loom for HVAC Systems, Some Water Heaters

Here is an end-of-the-year reminder of two changes planned for early 2015 for HVAC systems and some water heaters.
  • New regional standards for furnaces, air conditioners and heat pumps have been approved by the federal Department of Energy (DOE) for units installed in homes after Jan. 1, 2015. Get the details in this NAHBNow post from November.
  • Custom builders and others who install extra-large water heaters should also be aware of new requirements that go into effect for electric and gas models produced after April 15, 2015. There are alternatives, though: Get the details here.

Thursday, December 4, 2014

New Code Cost Requirement Benefits Builders and Buyers

In a big win for Home Builders and the home buyers we represent, the International Code Council (ICC) has taken a significant step forward in ensuring that code change proposals come with disclosure of their price tags.

In its press release announcing the opening of the 2015/2016/2017 code development cycle, ICC also announced that it will require all advocates to include the costs associated with any proposals introduced along with the paybacks, where appropriate.

It’s exactly what NAHB Chairman-elect Tom Woods asked for when he addressed the ICC board on September 29 and called on code change proponents to provide “quantitative information regarding the magnitude of the expected increase in construction costs.”

In an official statement lauding the ICC ruling on cost estimates, NAHB Chairman Kevin Kelly said:

“NAHB commends the ICC for approving this landmark ruling that will require all code change proposals to include cost estimates. By acknowledging that costs are an important factor in determining the merit of code change proposals, this will make the building codes process more cost-effective and affordable. In turn, this will help keep housing costs down, enable builders to construct more energy-efficient homes and allow more young families to enter the new home buying market.”

This issue has been an important concern for Home Builders, as noted in this recent Eye on Housing blog.

To learn more about the ICC and the code development process, NAHB has provided a code toolkit that includes suggested amendments to make the latest versions of the 2015 family of ICC codes more affordable and practical. HBA members must be logged in to nahb.org to download and view the toolkit.

Tuesday, June 10, 2014

Study suggests modern building codes can reduce energy usage

How big a role can building codes play in reducing energy waste?

That is the question economists at the University of Oregon and Yale University sought to answer by comparing monthly utility bills of 2,200 Gainesville, FL, homes built three years before and three years after Florida strengthened it building code in 2002.

According to the study, homes built after the change consumed, on average, 4 percent less electricity and 6 percent less natural gas—savings that homeowners achieved in a variety of ways, including using less-leaky air ducts, more-heat-resistant windows, better insulated attics and certain white roofing products.

The report estimated that the cost of compliance with the new code was less than $1,000 per house, with an average recoupment time for home owners of about 7 years.

Read the complete article: online.wsj.com.

Friday, May 23, 2014

Builder Breakfast - THIS Thursday May 29th at 7:30am Sponsored By PestBan!

There will be a Builder Breakfast on Thursday May 29th at 7:30am. Featuring Buddy Skinner, Assistant Building Codes Administrator with the City of Greenville.
This event is open to builder members only and will be held at Tommy's Ham House.

Please contact the HBA office at 864-254-0133 or email Crystal Yanes at cyanes@hbaofgreenville.comto register or for more information.

Thursday, January 16, 2014

City of Greenville revises enforcement on installation of grounding electrode


For several years the City of Greenville has required that a Grounding Electrode be encased in concrete in the foundation system of a newly-constructed house. In addition to the expense of compliance, theft became a problem as thieves began stealing the 4 gauge copper wire that is fastened to the Grounding Electrode and left protruding from the foundation. Repairs include welding a new portion of wire to the remaining wire if practical, or encasing a new Grounding Electrode in a new section of concrete, in contact with the earth, where at least two inches of concrete covers the Grounding Electrode.

At your Home Builders Association's request, the city reviewed and modified this requirement.

Encasing the Grounding Electrode is now required only when rebar is embedded in the foundation. The code requires that rebar in a foundation be bonded to the earth. If rebar is not present in the foundation, a Grounding Electrode, or more than one when required by the code, may be driven into the earth.

When encasing the Grounding Electrode in the foundation is required, consider these options to protect against theft:
  1. Bury and mark the wire after inspection to deter theft.
  2. Install a galvanized or other rust-resistant Grounding Electrode so that a portion of the rod protrudes from the foundation, preferably facing the inside of the crawl space or basement, and mechanically fasten the wire later in order to deter theft. Remember however that at least 20 feet of continuous rod, ½-inch in diameter, must be encased by at least 2 inches of concrete. When more than one rod of shorter lengths is used, the rods must be properly connected.

Friday, November 22, 2013

Code Amendment on Window Fall Protection Clarified

Your Home Builders Association successfully clarified an amendment to the building code relating to window fall protection.  The amendment was written improperly when it was adopted originally, which caused confusion in enforcement. 

For clarification, the following code amendment is adopted:

Window Protection – R312.2.1 as written is deleted and R312.2.2 now becomes the R312.2.1. R213.2 Window Fall Protection now reads; “Where window fall protection is provided it shall be installed in accordance with sections R312.2.1.

As a note, the get-out-of-jail-free card is R310.1.4 – Operating Constraints. This section states, “emergency escape and rescue openings shall be operational from the inside of the room without the use of keys, tools or special knowledge.”

It was the association's position, in advocating for the amendment above, that the Window Protection section conflicted with the Operating Constraints section.  The Building Codes Council agreed.

Wednesday, October 30, 2013

Avoid Electrical Inspection Failure on Your Next Project

Top Electrical Code Violations for Residential Permits
Source: City of Greenville

According to Buddy Skinner, City of Greenville Assistant Building Codes Administrator, 25 percent of all electrical inspections on single family residential projects fail.  Below is a list of the top reasons for inspection failures:
  1. Receptacle outlets should be located so that one can be reached within 6-feet measured along the wall surface in either direction. Outlets should also be located on any wall space 2-feet or larger. (2012 International Residential Code E3901.2)
  2. Receptacle outlets on kitchen counters should be located so that one can be reached within 2-feet measured along the wall surface in either direction. Outlets need to be installed above any kitchen counter 12-inches or wider. (2012 IRC E3901.4)
  3. Seal all drilled or notched holes in top and bottom plates with an approved material. (2012 IRC R302.11)
  4. Any neutral conductors (white in color) used as a phase conductor for a 220-volt circuit should be marked with black tape. This is commonly seen on conductors feeding a water heater or mechanical unit. (2012 IRC E33407.1 and E3407.2)
  5. Receptacles cannot be installed within or directly over a bathtub or shower stall. (2012 IRC E4002.11)
  6. No light fixture or fan can have suspended parts within 3-feet horizontally or 8-feet vertically from the top of the bathtub rim or shower stall threshold. (2012 IRC E4003.11)
  7. Watch the number of conductors that are installed in electrical boxes. A standard 20-cubic inch nail-on electrical box can have two romex wires and a device. A 22-cubic inch nail-on electrical box can have three romex wires and a device (2012 IRC E3905.12)
  8. Provide at least 6-inches of wire for device connection at each electrical box. (2012 IRC E3406.11.3)
  9. Arc-fault circuit protection is required for all circuits within a dwelling except for those required to be ground-fault protected. Wiring that supplies only smoke detectors do not have to be arc-fault protected. (2012 IRC E3902.12)
  10. In new dwelling units that have attached garages or fuel-fired appliances, carbon monoxide alarms must be installed outside each separate sleeping area near the bedroom or bedrooms. (2012 IRC R3015)
  11. Make sure that the bonding device is properly installed on all temporary power poles. (2012 IRC E3609)
  12. Where rebar is installed in footings, a bonding jumper must be connected from the rebar to the ground in the panel box. (2012 IRC E3608.1.2)
  13. Tabs in plastic boxes are designed to secure conductors and should not be removed. (2012 IRC E3403.3)
  14. Outdoor receptacles are required at grade level (not higher than 6’6’’) at the front and back of every dwelling and on every porch and balcony. (2012 IRC E3901.7)
  15. Observe burial depth requirements for underground cables and raceways (2012 IRC Table E3803.1)
  16. Nonmetallic cable (Romex) can only be used in dry locations (2012 IRC Table E3801.4) Note: Romex cannot be used in conduit outside to feed a mechanical unit.
  17. Ground-fault protected outlets are required in the crawl space and basement. (2012 IRC E3902.4 and 3902.5)

Thursday, October 17, 2013

NAHB: 2015 ICC Hearings: The Good, the Bad and the Ugly

Your Home Builders Association defeated 85 percent of the code changes it opposed, and passed 60 percent of the code changes it supported
 
The International Code Council, the private, nonprofit association of building code officials, cities, counties, and states, and interested businesses met last week in Atlantic City New Jersey for final action on more than 2,000 proposed changes to the International Codes series of building codes for the 2015 codes cycle.  NAHB scored some impressive wins but also suffered some unfortunate setbacks.

The Good

The NAHB Construction, Codes and Standards staff and builder volunteers provided excellent testimony at the hearings, and NAHB was successful on 85% of the hundreds of proposals that the association supported or opposed for the 2015 IRC.

Of particular importance to the home building community are five key proposals that NAHB fought against to keep building codes flexible, cost effective and product-neutral. NAHB’s success on these proposals represents total construction savings of up to $40,000 per house:

Additional Requirements for Exterior Foam Plastics. A proposal was disapproved that would have required all single-family homes or townhouses with foam plastics in the wall or roof system within 10 feet of the property line to be protected on both the interior and the exterior by a thermal barrier. It also prohibited the use of any siding that includes foam insulation as a backer product.

Had this proposal been approved, it would have required builders to sheath the entire exterior of their homes in a layer of drywall or wood sheathing, or maintain a distance of 10 feet from all property lines. In some cases, this could have resulted in an additional cost of up to $20,000 per home.

Additional Stairs and Ramps. A proposal that would have required all single-family homes and townhouses with multiple levels to have a stair or ramp within 50 feet of any habitable portion of the home was disapproved. The 2012 IRC requires a single stairway or ramp to connect all habitable levels. If approved, the proposal could have cost builders anywhere from $10,000 to $15,000 per home.

Residential Accessibility. A proposal was disapproved that would have required all one- and two-family homes to be designed so people with disabilities could enter unassisted, have a zero-clearance entrance, an elevator or lift, an accessible bathroom, bedroom and (if on the accessible level) a kitchen with 40 inches of clear floor space at all counters. If approved, the cost of compliance would have been $2,000 to $3,000 per house.

Wood Deck General Provisions. Expanded provisions for constructing wood decks were approved in Atlantic City. Among provisions that were considered but were ultimately disapproved were guard post, stair stringer and lateral connection requirements that would have added at least $300 in additional hardware costs. Also, provisions that could have led to engineering being required for decks were limited in scope or defeated, saving approximately $1,000 in engineering design costs per home.

Foundation Walls in Flood Zones. A proposal that would have required reinforced short stem walls in riverine flood zones (FEMA Zone A) was disapproved. Cost savings are in the range of $300 to $1,000 per house, depending on height and total length of walls.

"The staff members from the NAHB Construction, Codes and Standards Department fought day in and day out on behalf of everyone in the residential construction industry," said Lee Schwartz, vice president of government affairs for the HBA of Michigan. "It’s not just the ICC hearings where these unsung warriors do battle; it’s at the NFPA, ASHRAE, ASTM, NFRC, ANSI and IAPMO committee meetings and hearings as well. Without their hard work and support, Michigan would not have won the code victories that we achieved in our state."

The Bad
While NAHB posted resounding victories for the 2015 edition of the IRC, only about 60% of the changes proposed in favor of cost-effective, energy-efficient new homes were approved for the 2015 IECC.

Key proposals to restore mechanical equipment trade-offs, and to provide trade-offs for building tightness and window area, were soundly defeated despite testimony from dozens of builders, NAHB staff and building officials.

"To date, six states have adopted the 2012 IECC and only one state has adopted it without reduced stringency," said Pennsylvania home builder Frank Thompson. “Clearly there is a disconnect between the model codes and what jurisdictions are willing to adopt."

"We need to be able to determine what is the best alternative for our customers," added Michigan home builder Don Pratt, who also serves as chairman of the NAHB Construction, Codes and Standards Committee.

The Ugly
Trade-offs are energy-neutral by definition and allow builders and their customers to make choices based on affordability, marketability, or just plain personal preference. Unfortunately, there was concerted effort by opponents of home builders to maintain the reduced flexibility of the 2012 IECC and mandate that builders meet the stringent requirement of the energy code without exception.

For instance, another energy-neutral proposal to allow a builder to get credit in the performance path of the code when installing solar panels was disapproved, with opponents arguing that builders could possibly skimp on insulation to save money.

The idea that a builder or home owner would spend tens of thousands of dollars on photovoltaic panels to save money on electricity costs and not appropriately insulate is simply ludicrous.

Common-sense proposals to improve the flexibility, cost-effectiveness and product neutrality of the energy codes were too often thwarted by a coalition of energy-efficiency advocates funded by those businesses with the most to gain from more stringent codes.

Product manufacturers also sent representatives to the hearings as well, and some of them gleefully admitted that the results would enable them to sell more insulation, windows or other products. These advocates – many of whom have never even set foot on a job site or know anything about how a home is actually built – talked in the abstract and called these code proposals "rollbacks."

Despite the best efforts of NAHB staff, home builders from across the nation who volunteered their time, and building officials who attended the hearings, they were ultimately unable to compete with those who fought against cost-effective and sensible code proposals.

Too many building officials did not have the funds or time to come to Atlantic City on a weekend to vote in favor of energy code changes that were necessary, practical and cost-effective. Consequently, eligible voters not involved with code enforcement influenced many of the critical proposals that were meant to fix the broken 2012 IECC.

Despite these setbacks, NAHB was still able to hold its own as the 2015 residential energy requirements will not be more stringent than the 2012 and could actually turn out to be a bit less stringent.

Moreover, adoption of the 2012 IECC is facing unprecedented resistance at the local level. State and local jurisdictions adopt building codes, and performance matters. Building officials from across the nation are unlikely to implement the 2015 IECC without significant amendments because it is too difficult to put into practice and too expensive to use.


Note: South Carolina has adopted the 2009 IECC by statute.  It will take action by the General Assembly and approved by the Governor to adopt the 2012 or 2015 IECC.  Your Home Builders Association opposes adoption of the 2012 IECC.

Friday, May 10, 2013

Building Code: New Design Values for Southern Yellow Pine Postponed

You may be aware that the American Lumber Standards Committee approved new design values for Southern Yellow Pine in all applications except #2 2x4.  Their rationale is that the rapid-growth rate for modern southern yellow pine has reduced its load-carrying capacity.

The new standards reduce the distance spanned by the various lumber dimensions by as much as 15 percent and were set to take effect June 1.  Click here to view the update conversion chart for Southern Yellow Pine.

However, your Home Builders Association learned today that the International Code Council has elected not to implement the new design values in the current code and will instead consider them for the 2015 building code.  In addition, NAHB has continued its efforts to have the new design values reversed and is currently challenging the validity of the American Lumber Standards Committee's findings.

Note however that the 2012 International Residential Code is scheduled to take effect in South Carolina on July 1.  You may be aware that a provision of the new code includes an increase in the dimension of floor trusses, when a gas appliance is placed in the basement or crawl space, in order to avoid fire-proofing the floor above the gas appliance.  Your Home Builders Association is working with the South Carolina Building Officials Association to develop a solution to this expensive new requirement.  Stay tuned.

Wednesday, April 3, 2013

Value of Membership: Cost-Effective Building Codes

Builder Review continues its highlight of the more than 100 initiatives by your HBA that have saved HBA members during the last year.  Below is another way your HBA is saving our members money.

Working for Flexible, Cost-Effective Building Codes. Keeping building codes flexible, cost-effective and product-neutral remains a top NAHB priority. Every year, your HBA analyzes thousands of proposed codes from mandatory fire sprinklers to energy conservation rules and prevents requirements that could add tens of thousands of dollars to the cost of building a new home without any appreciable benefit to home buyers.

According to the NAHB Research Center’s 2012 IECC Cost Effectiveness Analysis, the additional cost to build a home to the 2012 IECC relative to the 2006 IECC is $7,034. The majority of that increase – $5,668 – is associated with the changes between the 2009 and 2012 versions of the IECC. NAHB’s successful effort to prevent widespread adoption of the 2012 IECC energy code in several states was a victory for sensible, flexible, cost-effective regulation.  South Carolina is one of the states that has locked in the 2009 IECC.

In addition, your HBA has amended the 2012 IRC to insure that automatic fire sprinklers will not be mandated in new homes in South Carolina.  Two dozen additional amendments also approved for the residential code are set to be adopted with the code on July 1, 2013.

Class on stormwater permit and building code changes: FREE for builders members

The Storm Water Codes for Greenville County have been updated, as a courtesy and included in the price of your Builder Membership the HBA of Greenville will be hosting a class to highlight and educate you on these codes. The class will be held at Progress Lighting on April 11th beginning at 8 a.m with continental breakfast served and the meeting will conclude at 11:30 a.m.

Thank you GBS Building Supply for sponsoring the class and helping make the class free to Home Builders.

Speakers for this event include:
  • Jessica Chapman- PE, CFM Assistant City Engineer - Environmental
  • John McLeod- Chief Building Codes Officil
  • Steve Landrith- Chief Building Official for the City of Greenville
  • Judy Wortkoetter- PE, Greenville County Engineer.
For associate members of the HBA of Greenville the cost to participate in this class is $20 and $35 for non members.  To register for this class please contact Crystal Yanes at 864-254-0133 or cyanes@hbaofgreenville.com.

On another note the HBA of Greenville and the State HBA has been committed to adoption of the 2012 International Residential Code (IRC) in order to maintain affordable housing for all South Carolina residents by keeping required residential sprinklers out of the adopted code.  We are expecting this code to become effective in July.

Friday, March 15, 2013

NAHB: New Guide Helps Builders Navigate 2012 Residential Code

A new guide co-published by the National Association of Home Builders (NAHB) and the International Code Council (ICC) provides critical answers to the most frequently asked residential construction jobsite code questions. Available through BuilderBooks, NAHB’s publishing arm, the 2012 Home Builders’ Jobsite Codes: A Quick Guide to the 2012 International Residential Code, is a portable guide for home builders, contractors, inspectors, architects, engineers and other construction professionals. The convenient field guide is a quick reference to the 2012 International Residential Code (IRC) and provides easy-to-read code requirements for every aspect of residential construction.

The 2012 Home Builders’ Jobsite Code discusses the impact of 2012 code changes to ventilation requirements, wall construction, duct sealing and other areas. It also details new fire safety and hurricane protection measures and discusses topics such as:
  • blower door tests
  • whole-house mechanical ventilation
  • fire protection of floors
  • wall bracing methods
  • roof construction
  • hot water piping
  • high-efficiency lighting
  • gray water recycling

“This new guide is an excellent resource for building professionals to stay on top of the most recent code changes,” said NAHB Chairman Rick Judson, a home builder from Charlotte, N.C. “With its easy-to-use reference guide, glossary, illustrations, and availability in both compact printed version or e-book, it will be an invaluable asset on the job site. ”

Written by Stephen A. Van Note, the guide features more than 100 illustrations, tables and figures to help the reader understand specific code requirements, as well as a glossary that provides definitions of construction-related terms. A certified building official and plans examiner, Van Note has more than 15 years of experience in code administration and enforcement and more than 20 years of experience in the construction field, including project planning and management for residential, commercial and industrial buildings.

2012 Home Builders’ Jobsite Codes is meant to be of practical use on the jobsite, not as a substitute for the complete codes.

To purchase the new 2012 Home Builders’ Jobsite Codes: A Quick Guide to the 2012 International Residential Code, please visit BuilderBooks.com or call 1-800-223-2665. (ISBN 978-086718-696-3; Retail $21.95/NAHB Member $19.95). The Guide is also available as an e-Book at ebooks.builderbooks.com (Retail $14.99/NAHB Member $12.99).

Monday, June 11, 2012

Top 12 Actions on behalf of Home Builders, Number 7: Particiation in the Building Code Development Hearings

Builder Review Daily is highlighting the top 12 actions taken on behalf of Home Builders so far in 2012.

Number 7: Particiation in the Building Code Development Hearings

NAHB’s members greatly benefitted from their representation on six of the seven committees that met recently as part of the International Code Council’s 2012 “Group A” code development hearings for the 2015 I-Codes.

The complex code development process and its outcome directly affect every builder member of our organization, and require an extensive amount of expertise, effort and time on the part of our staff and member volunteers. In the latest code hearings covering primarily requirements for commercial and multifamily construction, just over 1,600 code change proposals were submitted. After careful study, NAHB took a position of support or opposition on 359 of those proposals and a “watch” position on more than 100 others. Thanks in large part to our representation on the convening committees and the diligent work done by our committee members, NAHB chalked up an over-80% success rate on the proposals that we supported/opposed. Our successes pertained to a long list of items, from ventilation requirements to guardrails, townhouse classification, egress windows, sealed roof decks, and more. NAHB committee and staff experts will next be determining what comments to submit prior to the ICC’s Final Action Hearings on the Group A code changes this coming fall. Contact: Gary Ehrlich (800-368-5242 x8545).

Friday, June 8, 2012

The Top 12 actions on behalf of Home Builders, Number 6: making fire sprinklers optional

Builder Review Daily is reviewing the Top 12 actions on behalf of Home Builders so far this year.

Number 6, keeping automatic fire sprinklers optional:

NAHB remains committed to the effort to maintain fire sprinklers as voluntary elements in new homes nationwide.

With the help of NAHB staff and resources available within the NAHB Fire Sprinkler Action Kit, our state and local HBAs have so far been successful in keeping mandatory sprinklers out of more than 36 states. NAHB is also diligently keeping track of efforts by the fire sprinkler advocates and providing our members with the necessary resources to effectively counter unfounded NFPA claims. 

In Columbia, the S.C. Building Codes Council again included a fire sprinkler mandate in the IRC 2012 proposed for adoption in the state.  However, they lacked the votes to approve the building code with the sprinkler mandate.  Your HBA of South Carolina continues to work diligently to keep sprinklers optional in South Carolina.  Unfortunately, if the sprinkler advocates continue to push for a sprinkler mandate, South Carolina may continue to use the 2006 building code for many years to come.

For more information about residential fire sprinklers or the NAHB code adoption action kits, contact Steve Orlowski (800-368-5242 x8303) or Mark Nix (803-771-7408).

Tuesday, January 10, 2012

IBHS Rates South Carolina Fifth Among Hurricane-Prone States

The Insurance Institute for Business & Home Safety, a research arm of the insurance industry with a testing facility near Chester, SC, released its ratings for 18 hurricane-prone states along the Atlantic coast.  The ratings evaluate the state's building code and its enforcement, code official certification and training, and contractor licensing.  South Carolina had the fifth highest rating, behind Florida, Virginia, New Jersey, and Massachusetts.

View the ratings for each state at disastersafety.org by clicking here.

From the IBHS press release, the report is the first of its kind, state-by-state assessment of individual state performance in developing and promulgating a residential building code system, which uses modern building codes, coupled with strong enforcement related activities to enhance the protection of homes and families.

“The report goes beyond just evaluating each state’s code system,” said Julie Rochman, IBHS president and CEO. “The report offers each state the detailed information and tools it needs to improve its building code process to better protect its citizens. It also gives interested citizens useful information so that they can understand the need for, and demand, better building codes.”

The report combines IBHS’ engineering expertise and regulatory research to examine the three main elements of a state’s building code system:
  • Code adoption and enforcement – Statewide mandatory code adoption and enforcement are the primary elements to require that the minimum standards of codes are utilized.
  • Code official training and certification - Code official training and certification are part of the regulatory scheme to ensure that code officials are properly educated, trained and tested in order to correctly enforce building codes.
  • Licensing requirements for construction trades - Licensing requirements for construction trades ensure that contractors and subcontractors are familiar with the sections of code that impact them, that they demonstrate minimum competency in their trade, and stay current with code requirements.
“IBHS hopes to work with all of the states included in this report – as well as the other jurisdictions across the country – to improve building code regulatory systems. Strong, well enforced codes are essential to effectively strengthening homes, businesses and communities against hurricanes and many other hazards that threaten the U.S.,” Rochman said.